Construction Updates

The official Lockport construction page can be accessed through this link.  
Downtown Lockport is working to make itself better than ever (while maintaining its Canal-city charm), and is currently going through construction to alleviate traffic congestion through downtown and heading towards and over the IL 7 (9th Street) high-level bridge.  At the same time, IDOT reports that segments of IL Route 7 and both sides of IL Route 171 have pressing safety improvement needs.  As part of the project, the City is replacing water mains & water service laterals and installing new street scaping.What’s being improved?

  • Traffic signal replacement
  • Adding left turn lanes on IL 171 (State Street)
  • Reconstructing on-street parking
  • Providing new ADA compliant sidewalks and crossings within the project area
  • Utility relocations, water main replacement, and all water service lateral replacement between our main and plumbed into the buildings (water main replacement and water service lateral replacement are funded by the City)
  • Filling the old coal vaults that currently reside under the sidewalks as a safety measure for both pedestrians and building owners
  • Installing new streetscaping

Latest updates

  • August 16, 2018 – Concrete work has been completed between 827 State Street and the southwest corner of State and 8th Street. D construction has continued sidewalk vault removal and gravity wall installation at 931 and 933 State Street. The old gas tanks in front of 1025 State Street have been removed, and IDOT is awaiting soil test results to determine if further remediation is required. Following that, watermain installation and water service installation will continue on the west side of the 1000 block of State Street. Surface restoration will quickly follow.
  • July 23, 2018 – D Construction has Completed installation of all gravity walls North of 921 State Street on the west side. Backfilling of gravity wall installations will begin next week following proper concrete curing duration. Structural Soil, which helps promote tree growth in urban environments, has been installed at all locations north of 829 State Street. A concrete curb planter mockup will be installed on the southwest corner of 8th/State this week with concrete flatwork and brick pavers to follow.
  • July 9, 2018 – The Contractor has begun demolition of existing sidewalk vaults. Forming of the proposed gravity walls on the west side of State Street will begin on Monday 7/9/18 and poured by the end of the week. The electrician has begun installation of Light pole foundations and will continue with conduit installation on Monday 7/9/18. Once the electrician moves far enough along with conduit, the contractor intends to begin installation of the first planter bed, pcc sidewalk and brick pavers from 8th Street south to 9th Street.
  • June 18, 2018 – D Construction has finished all but one water service on the west side of State between 8th and 10th Streets. The base course for the parking bay on the west side of the street has been set. Concrete curb will be poured this week.
  • June 4, 2018 – Water service installation on the west side of the 800 and 900 blocks of State Street is underway and will continue through the end of the week. Water main installation south of 10th Street has been postponed due to the discovery of an old gas tank that requires specialized removal. Full sidewalk vault removal and gravity wall installation is scheduled to begin this week on the west side of State Street between 8th Street and 10th Street.
  • May 21, 2018 – D Construction began installation of 8” watermain, south of 10th Street on the west side of the road. Water service installation was delayed until the beginning of this week and will begin tomorrow.
  • May 7, 2018 – D Construction has completed water main installation on the west side of State Street between 10th and 8th Street. After the main is properly tested, D Construction will begin installation of water services, gravity walls, and water meters.

State Street Reconstruction (from 8th Street to 10th Street)

Scheduled Start Milestone Major Work Scheduled Completion
2/19/2018 Pre-Staging Install temporary traffic signals

Install temporary lighting
Complete
3/26/2018 Stage 1

West Side
Water main installation

Sidewalk removal
Complete
5/7/2018 Stage 1

West Side
Gravity wall installation (against buildings)

(Pedestrian walkway moved to parking lane)
6/1/2018
6/4/2018 Stage 1

West Side
Curb and sidewalk preparation 6/11/2018
6/12/2018 Stage 1

West Side
Curb installation

Sidewalk installation
Roadway base installation
6/26/2018
6/27/2018 Stage 1

West Side
Electrical work

(Temporary traffic signals and lighting)
7/10/2018
7/11/2018 Flip traffic to west side 7/11/2018
7/11/2018 Stage 2

East Side
Water main installation

Sidewalk removal
9/4/2018
9/5/2018 Stage 2

East Side
Gravity wall installation (against buildings)

(Pedestrian walkway moved to parking lane)
10/2/2018
10/3/2018 Stage 2

East Side
Curb and sidewalk preparation 10/10/2018
10/11/2018 Stage 2

East Side
Curb installation

Sidewalk installation
Roadway base installation
10/25/2018
10/26/2018 Stage 3 Roadway surface removal

Roadway surface installation
11/8/2018
11/9/2018 Stage 3 Pavement markings 11/15/2018
11/16/2018 Stage 3 Remove temporary traffic signals

Remove temporary lighting
11/22/2018
11/16/2018 Stage 3 Remove temporary traffic lanes 11/29/2018

IL 171 (State Street)

Scheduled Start Milestone Major Work Scheduled Completion
6/12/2018 Total Reconstruction Install sidewalks, planters, trees and plantings,

railings, bicycle racks, trash receptacles,

drinking fountain, clock, ornamental lighting, etc.
8/1/2019

 

Page last updated:  June 5, 2018

X